01 / The task
The preferred sequence is not yet supported.
The base case assumes works complete by month six, with rent from month seven at £1.2m a year. A contractor’s indicative programme instead points to month eight, while the leasing note describes month nine as the earliest plausible occupation. Neither is committed. The team must reconcile the sources, not merely list delay as a risk.
I1 · Base case / W1 · Contractor programme / L1 · Leasing note
02 / AI contribution
Give the team a connected view of the decision.
AI links works completion to occupation and income, surfaces conflicting dates and helps explore coherent alternatives. This can give the team a clearer basis for reasoning across the case. The architecture must distinguish dependencies supported by sources from assumptions and generated possibilities.
A plausible scenario can inform judgement without establishing its probability.
03 / Expert judgement
Turn analysis into a view and actionable conditions.
The team interprets which assumptions can move together, examines a six-month delay scenario and identifies the delivery, leasing and funding conditions that matter. It uses the analysis to form or revise its view. Expert attention is directed to consequential uncertainty rather than every generated variation.
The rent timing calculation is one input. Costs, financing and the wider investment case still need analysis.
04 / Recorded decision
Make the conditions specific enough to act on.
Return the paper with source-backed timing assumptions, a coherent downside and explicit conditions for delivery, leasing and funding review. Record what would change the recommendation and who must resolve each open point. The committee retains the investment judgement.
The example proposes a better paper; it does not recommend buying, lending or proceeding.